SR No.2/2018 in Unnumbered CCP of 2018 Subashini Thulasiram Rep. by PoA B. Jayalakshmi v/s SPR & RG Constructions Pvt. Ltd.,

Decided On20 Dec 2018
AppellantSubashini Thulasiram Rep. by PoA B. Jayalakshmi
RespondentSPR & RG Constructions Pvt. Ltd.,
Downlod
Summary

The complainant u/s 31 read with section 71 of RERA Act, 2016 seeking direction to the respondent to pay Rs. 20,00,000-/ as compensation together with interest 24% p.a from 31.05.2015 till the date of refund as per the section 18(3), section 14 in volation of sanction plan and approvals and section 19(1) of the RERA Act 2016, for not providing the information as to the status of the environmental clearance. In the result, the complaint is ordered to be numbered, If found, otherwise proper.