156/2017 to 158/2017 and 139/2018 to 142/2018 Mary Stella & 6 Others v/s Pacifica (Chennai Project) Infrastructure Pvt. Ltd.,

Decided On08 Feb 2019
AppellantMary Stella & 6 Others
RespondentPacifica (Chennai Project) Infrastructure Pvt. Ltd.,
Downlod
Summary

The Authority has received complaints from the allotees of Pacifica (Chennai Project) Infrastructure Pvt. Ltd.,for non delivery of the flats of the projects "Pacifica Aurum (Phase II - Pride Tower)" at S.F.Nos.89/1A pt, etc., of Padur Village, Kancheepuram District and S.F.Nos.198/10, 199/5 of Pudupakkam Village, Chengalpet Taluk, Kancheepuram District. in land bearing falling within the jurisdiction of Mamallapuram local planning area.The project comes within the ambit of "Ongoing Project" covered under the section 3 of the ACT..The Pride project is thus registered before TNRERA . SO The respondent is directly to registered the project with TNRERA within 2weeks from date of this order..