Haryana RERA Orders MRG Infrabuild to Reinstate Flat and Pay Delay Compensation
Dated on: Monday 1st December 2025Haryana RERA has ordered MRG Infrabuild to restore a cancelled flat in its “The Meridian” project after finding the builder’s action unjustified. The buyer had already paid more than the unit’s total cost, yet the developer cancelled the allotment without giving proper notice and without offering timely possession. RERA ruled the cancellation invalid and directed the builder to reinstate the unit within 30 days. The authority also instructed MRG Infrabuild to pay interest-based compensation for the construction and possession delay as per prescribed RERA norms.