Time schedule under Andhra Pradesh RERA
- General
- Author: Riya Kapoor
Highlights
The Real Estate (Regulation & Development) Act, 2016 is considered as one of the landmark legislations passed by the Government of India.
ts objective is to reform the real estate sector in India, encouraging greater transparency, citizen centricity, accountability, and financial discipline
The Real Estate (Regulation & Development) Act, 2016 is considered as one of the landmark legislations passed by the Government of India. Its objective is to reform the real estate sector in India, encouraging greater transparency, citizen centricity, accountability, and financial discipline. This is in line with the vast and growing economy of India as in future many people will be investing in real estate sector. All sections of the Real Estate (Regulation & Development) Act, 2016 came into force with effect from 1st May, 2017. The Andhra Pradesh Real Estate (Regulation & Development) Rules, 2017 was approved by the Government of Andhra Pradesh and notified on March 27, 2017.
Time Schedule For Various Issues Under The Provisions Of The Real Estate(R & D) Act,2016 And AP Real Estate(R & D) Rules,2017:-
Task | Time |
Establishment of Regulatory Authority & Appellate Tribunal (from 1st May 2016) | 01 year |
The web-based online system shall be operationalized (from the date of establishment of regulatory authority). | 01 year |
The application shall be submitted by the promoters for ongoing projects, from the date of commencement i.e, 1st May 2017 | 3 Months |
To issue the registration certificate of a project from the date of submission | 30 days |
To issue the registration certificate of an agent from the date of submission | 30 days |
Redressal of complaint from the date of filing | 30 days |
Withdrawal of registration of project by Promoter | 30 days |
Redressal of grievance filed before the appellate tribunal | 60 days |
Handing over of possession to the allottee by the promoter | 60 days |
Timeline to revoke the Registration from the date of issue of notice | Not less than 30 days |
Contact us now for your RERA Registration !!
Latest Blogs
- Key Highlights of Budget 2025 and Their Effect on Indian Real Estate Sector
- Best Practices for Real Estate Agents to Build a Successful RERA-Compliant Business
- Delayed possession and compensation under RERA
- The Power of RERA Authority to Impose Penalties on Builders
- Project Extension in RERA: What Builders Need to Know
- Rights of buyer under RERA
- Delhi RERA Agent Procedure for Re-validation or Renewal
- MahaRERA guidelines for Real Estate agent training and certification
- Force Majure Clause in RERA
- All you need to know about Relinquishment Deed
Copyright © 2025 RERA Filing. All rights reserved.