Guidelines for completion of project in Madhya Pradesh RERA

Guidelines for completion of project in Madhya Pradesh RERA
  • General
  • Author: Riya Kapoor

Highlights

  • Government of Madhya Pradesh implemented the Real Estate (Regulation and Development) Act and established Madhya Pradesh Real Estate Regulatory Authority on May 1, 2017. Mr. Anthony de Sa, I.A.S (Retd.) is the chairman of M.P. Real Estate Regulatory Authority.

  • The RERA (Real Estate Regulation and Development) Act has been established to safeguard the interest of the home purchasers.

  • It also promotes good investments in the sector for real estate. The RERA bill was passed in the Lok Sabha on 15 March 2016.

The RERA (Real Estate Regulation and Development) Act has been established to safeguard the interest of the home purchasers. It also promotes good investments in the sector for real estate. The RERA bill was passed in the Lok Sabha on 15 March 2016.

Government of Madhya Pradesh implemented the Real Estate (Regulation and Development) Act and established Madhya Pradesh Real Estate Regulatory Authority on May 1, 2017. Mr. Anthony de Sa, I.A.S (Retd.) is the chairman of M.P. Real Estate Regulatory Authority.

Every project is required to give completion date while registering the project.

 

At the time of completion of every project, following guidelines are required to be followed

in MPRERA :-

1. Obtain Completion Certificate from the respective Competent Authority for the Project.

2. Mention actual project completion date as well as the Completion Certificate issue date on the RERA website.

3. Enclose a scanned copy of Completion Certificate issued by the Competent Authority.

4. Submit Format 1C - Engineers Certificate on completion status.

5. Submit Format 2C – CA Certificate on completion status.

6. Enclose photographs (at least 5) in which completion of the project along with external development can be ascertained.

7. These documents may be submitted within the period of submission of the quarterly report for the quarter in which the project completed.

 

For any assistance regarding completion of project in RERA, contact us.

 