Delay possession charges to be paid ordered by HRERA
Dated on: Saturday 17th August 2019Exercising the power under Section 37 of the RERA Act, 2016, the HRERA ordered Emaar MGF Land to pay the delay possession charges @10.60% p.a. from the committed date of possession to the actual date of delivery of the property for its project Palm Hills situated in sector 77, Gurugram. Although being served with the notice, the developer didn’t appear and the concerned amount of charges are to be paid within 90 days from the order date.