DLF Homes to pay Rs 22.3 lakh to 13 Panchkula flat buyers as per consumer forum orders

Dated on: Monday 22nd May 2017

The State Consumer Disputes Redressal Forum has said that since the realtor failed to complete construction and deliver possession within the stipulated period and extended one-year period, it is responsible for delays and deficiency in service and their appeal for allowing them escalation cost of construction as well as land holding amounts to seeking an amendment of the terms and conditions of the agreement stands rejected.

More News