Haryana RERA has instructed BPTP Limited to refund ₹18.12 lakh to a homebuyer along with interest, citing delay in project delivery. The buyer had booked a property but did not receive possession within the promised timeframe. The developer had cancelled the allotment due to alleged non-payment, but the authority ruled that the delay and failure to refund made the builder liable. It also dismissed the argument that the complaint was time-barred, calling it an ongoing issue. The order highlights that builders must fulfill commitments and protects homebuyers from unfair practices in the real estate sector.