Haryana RERA has dismissed a developer’s plea seeking recovery of pending instalments and additional compensation from homebuyers. The authority clarified that the builder-buyer agreement already outlines penalties, such as interest on delayed payments, and no extra relief can be claimed beyond those terms. It stressed that RERA cannot be used to extend contractual rights or impose additional liabilities on buyers. The case involved a developer attempting to recover dues along with damages, which the authority found unjustified. As a result, the complaint was rejected, and both parties were directed to bear their own legal expenses without any further relief granted.