Telangana RERA has directed Jayathri Infrastructures to refund Rs 9 lakh each to buyers after failing to deliver its “Western Galaxy” project in Gopanpally, Hyderabad. Over 20 complaints were filed, citing no construction progress and land ownership issues. The project was also not registered under RERA, violating Section 3 of the Act. Buyers alleged that despite multiple promises, there were no signs of development. RERA termed the actions misleading and ruled in favor of the complainants, ordering the refund along with interest and costs within 45 days.